“the ministry’s debts equaled 56 percent of its assets and could reach $455 billion, or 70 percent of its assets, by 2020.” “A person with ties to the ministry said that the concrete bases for the system’s tracks were so cheaply made, with inadequate use of chemical hardening agents, that trains would be unable to maintain their current speeds of about 217 miles per hour for more than a few years. In as little as five years, lower speeds, possibly below about 186 miles per hour, could be required as the rails become less straight, the expert said. Strong concrete pillars require a large dose of high-quality fly ash, the byproduct of burning coal. But the speed of construction has far exceeded the available supply, according to a 2008 study by a Chinese railway design institute.”
is currently located in Shanghai, PRC
Submit
| www.flickr.com |
February 19, 2011
Chinese Railway Ministry, Liu Zhijun is fired